American Airlines Central Fulfillment Center (AA CFC)

American Airlines Central Fulfillment Center (AA CFC)

Project Budget: $69,138,315

35 Acres
Ground Up / Industrial / Office
DFW Airport, Texas

35 acre development consisting of rerouting DFW Airport Terminal utilities and power, 3 roadways, Glycol discharge lines, ATMOS primary gas lines, ONCOR underground primary electrical duct banks, transformers and switchgears, DFW Communication duct banks and 4 acres of underground detention ponds – all to make room for a 394,143sf fully conditioned concrete tilt wall warehouse with insulated panels and 30,465sf of office finish-out, a 68,000sf Autostore parts storage conveyor system, completely racked warehouse with tire storage and an integrated state of the art IT system, and noted to be completed during the historic COVID19 pandemic, and completed ahead of schedule and under budget